Northgate has been ramping up exploration activities in keeping with an accelerated development plan. We have recently announced positive results from our feasibility study and are scheduled to commence construction in the summer of 2010.
|
|
Recent Achievements
|
- Completed the final feasibility study for the project (January 2010)
- Added 2.8 million ounces of contained gold on the property
- Received board approval for the development of the Young-Davidson mine
- Signed an IBA with the Matachewan First Nation
- Appointed an EPCM contractor and awarded a shaft development contract
- Received key permit for the development of the Young-Davidson Mine.
|
| Project Timeline |
- Construction set to begin in August 2010.
- Commissioning in late 2011
- Target full production in 2012
|
|
| Recent Press Releases |
|
Northgate Minerals Releases Final Feasibility Study for the Young-Davidson Project (dated January 25, 2010)
|
|
Flag Raising Ceremony to Celebrate Development of Northgate's Young-Davidson Mine (dated March 4, 2010)
|
|
Mine Trainees Strike Gold (dated May 29, 2010)
|
|
Northgate Minerals Receives Key Permit for the Development of the Young-Davidson Mine (dated July 2, 2010)
|
|
Northgate Minerals Intersects New Gold Zone of 3.46 Grams per Tonne Over 79.5 Metres at Young-Davidson (dated July 6, 2010)
|
|
|
|
Windows Media Files – Ramp Development and Deposit Rotation |
|
Ramp Development |
|
|
|